As an exhibitor, it is important to keep track of all deadlines to ensure smooth participation in PROVADA 2026. On this page, you will find a complete overview of all important dates—from submitting your stand design and logo to providing program information and reserving meeting rooms.
| Action | Deadline |
|---|---|
| Submission of student day program (for participating exhibitors) | Thursday, April 16 |
| Submission of stand design + sound plan | Friday, May 1 |
| Contact details for stand builder + contact details for sound engineer | Friday, May 1 |
| Submission of final logo | Monday, May 11 |
| Stand construction approval for adjacent exhibitors | Tuesday, May 6 |
| Request for extra construction day | Friday, May 22 |
| Post information about meeting on provada.nl for inclusion in PropertyDay* | Tuesday, May 20 at 12:00 p.m. |
| List meeting and post information on provada.nl** | Friday, June 5 at 12:00 p.m. |
| Reservations for E-Rooms and C-Rooms | Friday, June 5 at 12:00 p.m. |
| Requests for audiovisual equipment | Tuesday, June 2 |
| Submission of presentation | Thursday, June 4, 5:00 p.m. |
Please note: material delivered after the deadline may not be processed. Please also check the RAI deadlines for technical services such as electricity, rigging, catering, and furniture, for which early bird discounts are available.
If we have not received your information by the above dates, PROVADA is not responsible for not being able to mention/reserve it.
* PropertyDay is the trade fair magazine containing the program overview, among other things, and will be distributed on days 1, 2, and 3.
The program overview lists the time, title, organization, and location.
Please note: the title of the meeting must refer to the content and be linked to a specific time slot.
** For the online program overview, you can enter the title with invitation text for the public.
This is not intended for posting general announcements for stand visits.
PROVADA checks texts before publication and may decide not to post entered meetings if the information is incomplete.
| Action | Deadline |
|---|---|
| Early bird discount (20%) rigging, electricity | Tuesday, May 12 |
| Order electricity (more than 3KW), internet, water, rigging, staff | Thursday, June 8 |
| Order cleaning, furniture, and refrigerators | Thursday, May 28 |
| Late fee 20% | Thursday, June 4 |
| Customized Catering* | Tuesday, May 12 |
| Last chance to order electricity and fire extinguishers | Monday, June 8 |
*PLEASE NOTE: All catering quotes must be confirmed by this date. The RAI can process requests on this date, but cannot guarantee that this will still be possible.